Project change log template. Keep the decision clear.

Inside the free Excel change log

Preserve the request, assessment, and decision.

Download an editable workbook with instructions, a blank change log, and a fictional worked example. Record the request before assessing its effects, then capture the named decision and baseline changes.

RequestImpact assessmentDecisionBaseline update
CR-014: add mobile approval screenTwo weeks and an estimated $8,000 vendor costSponsor approved on 12 OctoberScope v3, milestone plan v5, and cost forecast updated

The example is fictional. Replace its authority, dates, costs, and baseline references with your project’s agreed process.

What belongs in a project change log?

Give each request a stable ID, requester, description, and rationale. Assess scope, schedule, cost, and deliverable effects before recording the decision authority, disposition, effective date, and next action.

What happens after approval?

Update the affected project baselines, assign the follow-through, and communicate the new commitment. Keep rejected and deferred requests with a short decision reference.

Download the free template

Compare the approved charter · Report the change in project status · Connect decisions to RAID